WATER 2005 drill terminated

WATER 2005 drill was officially terminated on Sunday 24 July 2005 at 9.00 am., following the order issued by Petr Beran, the officer-in-command of the exercise.

According to the communication of the Operational centre of the City of Prague Crisis Staff, the time schedule of flood protection barriers disassembly has been as follows:

Saturday 23 July 2005

  • 17:15  OS HZS Praha (Prague Fire Rescue Repartment Administration) issued order for the intervention of Fire Fighters corpses (SDH) for disassembly of flood protection barriers.
  • 18:00 flood protection barriers disassembly by SDH corpses started
  • 19:23 flood protection barrier disassembly finished in Výtoň area
  • 21:41 traffic fully resumed in the area of KOMOKO (Bezová) underpass
  • 21:41 traffic fully resumed in the area around Four Seasons hotel 
  • 22:37 flood protection barrier disassembly finished on Masaryk Embankment, traffic resumed
  • 22:55  traffic resumed on Dvořák Embankment, Ludvík Svoboda Embankment and in the section from Hlávka Bridge to Negrelli viaduct
  • 23:48 flood protection barrier disassembly finished on Hořejší nábřeží (Upper Embankment) and Janáček Embankment, traffic fully resumed at the same time

Sunday 24 July 2005

  • 1:18 flood protection barrier disassembly finished on Smetana Embankment, traffic fully resumed at the same time
  • 6:05 flood protection barrier disassembly within the WATER 2005 drill finished on the whole Prague territory, including transportation of the disassembled barriers into warehouses. Traffic in the capital resumed in the full extent.
  • WATER 2005 drill officially terminated at 9:00 o’clock

Prague, 24 July 2005

 